QEP Partners/EQT Corporation, In the Matter of

Forum
FTC administrative order
Docket
C-4799
Order date
2023-10-10 (printed in the order)
Status in the FTC case catalog
Entered or issued, listed on the case page under 2023-10-10
Length of the order
Until 2033-10-10 (10 years from issuance of the order)
Source
Order text (PDF, ftc.gov) | FTC case page
Source file sha256
183625cdae45ce5d53e4003af275bafd4b67972ec00b2f0ed2f020bf24caaebd

Parties bound, as written in the order

Notices

Duties (35)

II: Required action

Before the Acquisition Date, amend the Acquisition Agreement and related agreements to remove any right of Quantum personnel to serve on EQT's board.

Who
Respondents
When
Due by the event “Acquisition Date”; date not public
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
prior to the Acquisition Date, Respondents shall amend and remove from any agreement relating to the Acquisition, including the Acquisition Agreement and any related exhibits, the right of any director, officer, partner, employee, or agent of Quantum to serve on the board of directors of EQT.

Quoted from the order text (PDF), clause II.

III.A: Prohibition

Quantum must not appoint or seek board representation at EQT or its covered entities, or have personnel serve as an EQT officer or director or in a decision-making role at an EQT Covered Entity.

Who
Quantum
When
No one-time deadline
How long
Until 2033-10-10 (10 years from issuance of the order)
Status
In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Quantum shall not, directly or indirectly: 1. Appoint any persons to the board of directors of EQT Corporation or any EQT Covered Entity

Quoted from the order text (PDF), clause III.A.

III.B: Prohibition

EQT must not have its directors, officers or agents serve simultaneously in a management capacity at Quantum, its operating entities or funds, subject to the Independent Director proviso.

Who
EQT
When
No one-time deadline
How long
Until 2033-10-10 (10 years from issuance of the order)
Status
In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
EQT shall not directly or indirectly, have any of its directors, officers, or agents serve simultaneously in any management capacity within Quantum

Quoted from the order text (PDF), clause III.B.

IV.A: Divestiture

Quantum must divest all EQT Shares no later than the Stock Divestiture Deadline.

Who
Quantum
When
Due by the event “Stock Divestiture Deadline”; date not public
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Quantum shall divest all the EQT Shares no later than the Stock Divestiture Deadline

Quoted from the order text (PDF), clause IV.A.

IV.B: Prohibition

Quantum must not sell EQT Shares outside the open market to a top-7 Appalachian natural gas producer without prior Commission approval.

Who
Quantum
When
No one-time deadline
How long
Runs until the event “divestiture of all EQT Shares”; date not public
Status
In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Quantum shall not divest any of the EQT Shares outside the open market to any entity that is one of the top 7 natural gas producers in the Relevant Area

Quoted from the order text (PDF), clause IV.B.

IV.C: Prohibition

Except as law requires, Quantum must not share non-public information about its EQT stock position or intent to sell or hold with EQT.

Who
Quantum
When
No one-time deadline
How long
Runs until the event “divestiture of all EQT Shares”; date not public
Status
In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Except as required by applicable law, Quantum shall not share with EQT any non-public information regarding its stock position or intent to sell or hold any of the EQT Shares

Quoted from the order text (PDF), clause IV.C.

IV.D: Prohibition

Before divesting the EQT Shares, Quantum must not give EQT non-public information about Quantum Covered Entities or seek non-public information about EQT.

Who
Quantum
When
No one-time deadline
How long
Runs until the event “divestiture of the EQT Shares”; date not public
Status
In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Quantum shall not, during the period prior to the divestiture of the EQT Shares: 1. Provide or attempt to provide to EQT Corporation or any EQT Covered Entity any Non-Public Information

Quoted from the order text (PDF), clause IV.D.

IV.E: Prohibition

Before the EQT Shares are divested, EQT must not give Quantum non-public information about EQT Covered Entities or seek non-public information about Quantum Covered Entities.

Who
EQT
When
No one-time deadline
How long
Runs until the event “divestiture of the EQT Shares”; date not public
Status
In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
EQT shall not, during the period prior to the divestiture of the EQT Shares: 1. Provide or attempt to provide to Quantum or any Quantum Covered Entity any

Quoted from the order text (PDF), clause IV.E.

V.A: Required action

No later than 10 days after the Acquisition Date, Quantum must appoint an independent trustee, after consulting Commission staff, to exercise voting rights on the Original EQT Shares.

Who
Quantum
When
Due 10 days, counted from the event “Acquisition Date”; date not public
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
No later than 10 days after the Acquisition Date and after consultation with Commission staff for purposes of conflict and bias, Quantum shall appoint a trustee (“Trustee”)

Quoted from the order text (PDF), clause V.A.

V.B: Required action

Quantum must grant the Trustee sole voting rights on the Original EQT Shares and direct the Trustee to vote proportionally to all other EQT shareholders.

Who
Quantum
When
No one-time deadline
How long
Runs until the event “divestiture of the Original EQT Shares”; date not public
Status
In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Direct the Trustee to vote the Original EQT Shares in an amount and in a manner proportional to the vote of all other EQT shareholders entitled to vote on a

Quoted from the order text (PDF), clause V.B.

V.C(3): Required action

Quantum must vote any Additional EQT Shares proportionally to the vote of all other EQT shareholders.

Who
Quantum
When
No one-time deadline
How long
Runs until the event “divestiture of all EQT Shares”; date not public
Status
In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Shall vote or cause to be voted such Additional EQT Shares in an amount and in a manner proportional to the vote of all other EQT shareholders entitled to vote on a

Quoted from the order text (PDF), clause V.C(3).

V.D: Prohibition

While holding EQT shares, Quantum must hold them as a passive investor: no proxy solicitation, no proposing shareholder actions, and no attempts to influence EQT management or operations.

Who
Quantum
When
No one-time deadline
How long
Runs until the event “divestiture of all EQT Shares”; date not public
Status
In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Quantum will hold such shares as a passive investor, it being understood that Quantum shall not:

Quoted from the order text (PDF), clause V.D.

VI: Prohibition

Quantum must not acquire Additional EQT Shares without prior Commission approval, subject to listed exceptions.

Who
Quantum
When
No one-time deadline
How long
Until 2033-10-10 (10 years from issuance of the order)
Status
In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Quantum shall not acquire any Additional EQT Shares without the prior approval of the Commission

Quoted from the order text (PDF), clause VI.

VII: Prohibition

Before divestiture of the EQT Shares, Quantum personnel must not serve as officer or director of a top-7 Appalachian gas producer without prior Commission approval.

Who
Quantum
When
No one-time deadline
How long
Runs until the event “divestiture of the EQT Shares”; date not public
Status
In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Quantum shall not, without the prior approval of the Commission, have any of its partners, employees, or agents serve simultaneously as an officer or director of any entity that is

Quoted from the order text (PDF), clause VII.

VIII: Prohibition

Quantum and EQT must not enter into an agreement not to compete with each other, other than one ancillary to the sale of a business, assets or company.

Who
Quantum and EQT
When
No one-time deadline
How long
Until 2033-10-10 (10 years from issuance of the order)
Status
In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Quantum and EQT shall not enter into any agreement not to compete with each other, other than in connection with, and ancillary to, the sale of a business, assets, or company.

Quoted from the order text (PDF), clause VIII.

IX: Prohibition

Before all EQT Shares are divested, Quantum and EQT must not enter into agreements or transactions with each other on Appalachian mineral rights or gas production without HSR notification or Commission prior approval.

Who
Quantum and EQT
When
No one-time deadline
How long
Runs until the event “divestiture of all the EQT Shares”; date not public
Status
In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Quantum and EQT shall not enter into any agreement or transaction with each other related to the acquisition of mineral rights or natural gas exploration

Quoted from the order text (PDF), clause IX.

XI: Divestiture

No later than the Acquisition Date, Respondents must have caused The Mineral Company to distribute its assets and discontinue operations, and eliminate its non-compete agreements.

Who
Respondents
When
Due by the event “Acquisition Date”; date not public
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
no later than the Acquisition Date, Respondents shall: A. Have caused The Mineral Company to distribute its assets to each of Quantum and EQT

Quoted from the order text (PDF), clause XI.

XII.D: Cooperation

Cooperate with and assist the Monitor, give access to personnel, information and facilities, not interfere, and pay the Monitor's fees and expenses.

Who
Respondents
When
No one-time deadline
How long
Runs until the event “Commission staff determines that Respondents have satisfied all obligations under Paragraph IV.A and files a final report”; date not public
Status
In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Cooperate with and assist the Monitor in performing his or her duties for the purpose of reviewing Respondents’ compliance with their obligations under this

Quoted from the order text (PDF), clause XII.D.

XIII.C: Required action

If a Divestiture Trustee is appointed, Quantum must execute a trust agreement within 10 days after the appointment.

Who
Quantum
When
Due 10 days, counted from the event “appointment of a Divestiture Trustee”; date not public
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Not later than 10 days after the appointment of a Divestiture Trustee, Quantum shall execute a trust agreement

Quoted from the order text (PDF), clause XIII.C.

XIV.A: Notice

No later than 10 days after issuance, send a copy of the order, complaint and Analysis to Aid Public Comment to board members and officers.

Who
Respondents
When
Due 2023-10-20 (10 days after issuance of the order)
Status
No public record of completion found. We have not found a public record showing this duty being carried out. Most compliance is reported privately to the agency and never published, so the absence of a public record does not mean the duty was not met.
no later than 10 days after this Order is issued, Respondents shall send a copy of this Order, the Complaint, and the Analysis to Aid Public Comment

Quoted from the order text (PDF), clause XIV.A.

XIV.B: Notice

For 5 years after issuance, send the order materials to each new board member, officer and director within 10 days of their appointment.

Who
Respondents
When
Due 10 days, counted from the event “an individual becomes a board member, officer, or director”; date not public
How long
Until 2028-10-10 (5 years from issuance of the order)
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
For a period of 5 years after this Order is issued, each new board member, officer, and director no later than 10 days after an individual becomes a board member, officer, or director

Quoted from the order text (PDF), clause XIV.B.

XV.A: Required action

Quantum must appoint an Antitrust Compliance Officer no later than 30 days from issuance, as part of an antitrust compliance program.

Who
Quantum
When
Due 2023-11-09 (30 days after issuance of the order)
Status
No public record of completion found. We have not found a public record showing this duty being carried out. Most compliance is reported privately to the agency and never published, so the absence of a public record does not mean the duty was not met.
No later than 30 days from the date this Order is issued, appoint an Antitrust Compliance Officer to supervise Quantum’s antitrust compliance program

Quoted from the order text (PDF), clause XV.A.

XV.B(1): Required action

Quantum must give antitrust compliance training to managerial personnel at QEP Partners no later than 60 days after issuance.

Who
Quantum
When
Due 2023-12-09 (60 days after issuance of the order)
Status
No public record of completion found. We have not found a public record showing this duty being carried out. Most compliance is reported privately to the agency and never published, so the absence of a public record does not mean the duty was not met.
No later than 60 days after this Order is issued;

Quoted from the order text (PDF), clause XV.B(1).

XV.B(2): Required action

Quantum must train a person within 30 days after they first become a manager at QEP Partners.

Who
Quantum
When
Due 30 days, counted from the event “an employee first becomes a person with managerial responsibility at QEP Partners, LP”; date not public
How long
Until 2033-10-10 (10 years from issuance of the order)
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
No later than 30 days after an employee first becomes a person with managerial responsibility at QEP Partners, LP;

Quoted from the order text (PDF), clause XV.B(2).

XV.B(3): Required action

Quantum must provide antitrust compliance training to managerial personnel at least annually.

Who
Quantum
When
No one-time deadline
How long
Until 2033-10-10 (10 years from issuance of the order)
Repeats
Every 1 year
Status
In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Provide in-person or online training concerning Quantum’s obligations under this Order and an overview of the Antitrust Laws

Quoted from the order text (PDF), clause XV.B(3).

XV.C: Recordkeeping

Quantum must maintain policies for confidential reporting, discipline for non-compliance, and retention of training and compliance records.

Who
Quantum
When
No one-time deadline
How long
Until 2033-10-10 (10 years from issuance of the order)
Status
In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Maintain policies and procedures for: 1. Managerial personnel to ask questions about, and report violations of, this Order

Quoted from the order text (PDF), clause XV.C.

XVI.A: Notice

Respondents must notify Commission staff within 5 days of the Acquisition Date and of completing the Mineral Company dissolution.

Who
Respondents (reports to: Commission staff)
When
Due 5 days, counted from the event “occurrence of the Acquisition Date or completion of the dissolution required by Section XI”; date not public
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
No later than 5 days after its occurrence, Respondents shall notify Commission staff via email at bccompliance@ftc.gov of:

Quoted from the order text (PDF), clause XVI.A.

XVI.B: Notice

Quantum must notify Commission staff within 5 days of completing the EQT stock divestiture and of acquiring any EQT shares not needing prior approval.

Who
Quantum (reports to: Commission staff)
When
Due 5 days, counted from the event “completing the divestiture or acquiring EQT Shares not requiring prior approval”; date not public
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
No later than 5 days after its occurrence, Quantum shall notify Commission staff via email at bccompliance@ftc.gov of the date on which it has:

Quoted from the order text (PDF), clause XVI.B.

XVI.C(1-2): Reporting

Quantum and EQT must each submit verified interim compliance reports 30 days after issuance and every 60 days thereafter for one year.

Who
Respondents (reports to: Commission)
When
Due 2023-11-09 (30 days after issuance of the order)
How long
Until 2024-10-10 (1 year from issuance of the order)
Repeats
Every 60 days
Status
Term has ended. The period this duty lasts for has run out under the order's own terms.
Respondent Quantum shall submit interim compliance reports 30 days after this Order is issued and every 60 days thereafter for one year;

Quoted from the order text (PDF), clause XVI.C(1-2).

XVI.C(3): Reporting

Each Respondent must submit annual compliance reports one year after issuance and annually for the next nine years, plus additional reports on request.

Who
Respondents (reports to: Commission)
When
Due 2024-10-10 (1 year after issuance of the order)
How long
Until 2033-10-10 (10 years from issuance of the order)
Repeats
Every 1 year
Status
No public record of completion found. We have not found a public record showing this duty being carried out. Most compliance is reported privately to the agency and never published, so the absence of a public record does not mean the duty was not met.
Annual compliance reports one year after the date this Order is issued and annually thereafter for the next nine years on the anniversary of that date

Quoted from the order text (PDF), clause XVI.C(3).

XVI.C(5): Recordkeeping

For 5 years after filing a compliance report, retain material written communications and non-privileged internal documents about order compliance; provide copies on request.

Who
Respondents
When
No one-time deadline
How long
Runs 5 years, counted from the event “filing a compliance report”; date not public
Status
In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
For a period of 5 years after filing a compliance report, each Respondent shall retain all material written communications with each party identified in each

Quoted from the order text (PDF), clause XVI.C(5).

XVII.A: Notice

Quantum and EQT must each notify the Commission at least 30 days before dissolution, acquisition, merger or other change that may affect order compliance.

Who
Respondents (reports to: Commission)
When
No one-time deadline
How long
Until 2033-10-10 (10 years from issuance of the order)
Status
In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Shall each notify the Commission at least 30 days prior to:

Quoted from the order text (PDF), clause XVII.A.

XVII.B: Notice

Notify the Commission no later than 10 days after a Quantum entity or EQT files a bankruptcy petition.

Who
Respondents (reports to: Commission)
When
Due 10 days, counted from the event “filing of a petition for bankruptcy”; date not public
How long
Until 2033-10-10 (10 years from issuance of the order)
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
No later than 10 days after Quantum Energy Partners VI, LP, Q-TH Appalachia (VI) Investment Partners LLC, QEP Partners LP, or EQT Corporation files a petition for bankruptcy

Quoted from the order text (PDF), clause XVII.B.

XVIII: Cooperation

On written request and 5 days' notice, give Commission representatives access to facilities and records related to compliance and permit interviews of officers, directors or employees.

Who
Respondents (reports to: Commission)
When
Due 5 days, counted from the event “written request and notice to the relevant Respondent”; date not public
How long
Until 2033-10-10 (10 years from issuance of the order)
Status
Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Access, during business office hours of the Respondent and in the presence of counsel, to all facilities and access to inspect and copy all business and other records and all

Quoted from the order text (PDF), clause XVIII.

XX: Term of the order

The order terminates 10 years from the date it is issued.

Who
Respondents
When
No one-time deadline
How long
Until 2033-10-10 (10 years from issuance of the order)
Status
In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
this Order shall terminate 10 years from the date it is issued.

Quoted from the order text (PDF), clause XX.